Phase 1:
Milbocker had a small crew on site this week working on the remaining punch list items from Phase 1.
Phase 2:
This Week:
- Montgomery completed the water main installation on Audley Drive.
- The north half of the water main on Audley Drive was pressure tested and disinfected.
- Montgomery may fill and pressure test the south half of the water main on Audley Drive today (Friday).
Next Week:
- Pending passing test results on the north half of the water main this afternoon (Friday), Montgomery will complete a water main tie-in at the north end of Audley Drive and Miramar Avenue.
- After the tie-in is completed, Montgomery will begin switching water services over from the existing water main to the new water main along the north half of Audley Drive.
- Montgomery will also work with the Plainfield Water Department to disinfect the new water main on the south half of Audley Drive.