Work completed this week:
- N Court St – Road building crews started grading the road and prepared for concrete crews to pour the curb and gutter.
- S Court St – Road building crews started grading the road and prepared for concrete crews to pour the curb and gutter.
- Walnut St – Constructed the flow channel in the sanitary sewer manhole at the Walnut/Court intersection.
- Vine St – Pressure testing the new water main, installed storm sewer at Walnut/Vine intersection.
- Grove St – Started stripping topsoil along the road shoulder in preparation for laying water main.
Upcoming Work:
Work anticipated next week:
- N Court St – Concrete crews will be on site to pour curb and gutter at the intersections.
- S Court St – Concrete crews will be on site to pour curb and gutter at the intersections.
- Vine St – Complete water main tie-in and install water services. Road building crews will be grading the road and prepare for concrete crews. Concrete crews will be on site to pour curb and gutter at the intersections.
- Grove St – Start installing new water main.