Work Completed this Week (October 26 – 30)

  • 50% of the water main was installed including the most difficult portion located in Court Street.
  • Storm sewer at Court Street was installed in anticipation of rebuilding the roadway.
 

Anticipated Work Next Week

  • Concrete footings will be poured on Monday or Tuesday of next week.
  • Curb and gutter will be installed along Court Street, paving of Court Street should be completed by the end of the week.
  • Construction staking will be completed for the proposed pavilion location, light poles, and storm sewer.