Progress Report

Private water service installation continued throughout the project area. As of January 31, twenty-six (26) of the thirty-seven (37) houses whose water service is available for connection from 2021 construction – 70% of the 2021 project area – have connected to the municipal water system. See status map above for reference.

Homeowners must schedule the work directly with the contactor they selected. Please contact Jeremy Kamp (contact info to the left) if you have any questions.

Water main pipe has been stockpiled along Packer Drive, just south of Rogue Hill Court, in preparation for construction to begin as soon as the snow melts in the spring!

April 2022
  • Dean’s will be back on site to install water main and water services along Rogue Hill Court, Rogue Hollow Court, and Packer Woods Drive.

Please contact any project representative to the left if you have questions or concerns.

 

What to Expect

February 2022 – Spring 2022
  • Private water service installation.
 
Spring of 2022
  • Water main and water services along Rogue Hill Court, Rogue Hollow Court, and Packer Woods Drive.