Work Completed this Week (November 9 – 13)

  • The water main installation was completed up to the future connection points, after final testing the water main will be connected at both ends.
  • Backfilling of the foundation walls of the new restroom building was completed.
  • HVAC, plumbing and electrical underground work was completed for the new restroom building.
 

Anticipated Work Next Week

  • Pressure testing and chlorination of the new water main will be completed.
  • Storm sewer installation will be started on the south half of the project.
  • Floor slab for the restroom building will poured.
  • Rough in for the site electrical will begin which will consist of conduits, handholes and layout for light pole bases.