We thank all of the residents for their collaboration and cooperation on the project so far. We also thank everyone in advance for their patience during construction. The Contractor will work as quickly as possible to complete the project and limit disruptions.

Tree removals and trimming will begin the week of February 18 in preparation for water main installation.

Water main work is currently scheduled to begin around March 16 (weather permitting). Work will begin on D Avenue, then proceed northward along 35th Street, and finally westward along CD Avenue. The water main will be pressure tested and chlorinated (to sanitize it) in sections as construction proceeds. Individual water services can be installed after each section of water main passes all pressure and sanitizing test. The project field engineer will be in contact with each resident soon to finalize details on the water service connections.