Work completed/in progress from this past week:

  • Lakewood closed between 160th and 152nd. Traffic detoured to James Street.
  • Lakewood closed between 152nd and 144th. Traffic detoured to Ottawa Beach.
  • 36″ transmission main construction commenced.
  • Installation of some dewatering, where required.
  • Continued staging pipe materials.
  • Pipe manufacturer visited site to review construction methods with contractor.

 

Anticipated activities for next week include the following:

  • Continue 36″ transmission main construction.
  • Water service verification and replacement (as necessary).
  • Utility locating.
  • Removal and replacement of large culvert just east of Harderwyk Ministries.
  • Mobilization of some HDD equipment.

 