A pre-construction meeting was held with Dykema Excavators and other project representatives on Thursday, April 9. Dykema Excavators plans to commence construction on Monday, April 20, pending receipt of final permits.

 

What to Expect Next Week (April 13–17)

You may see survey crews doing preliminary construction staking, utility companies marking the location of underground lines, and/or the contractor and subcontractors making preparations for construction.

 

Projected Timeline

 

Please share this information with your neighbors who may not have email or access to the internet.

Thank you for your patience and we look forward to a successful project!