Progress Report: Over the last two weeks Dykema has made good progress and has installed the majority of the water main along Northland Drive. Marksman Contracting, Dykema’s bore & jack subcontractor, has installed their pits on either side of M-44. Due to elevated groundwater levels, groundwater dewatering equipment was installed earlier this week to draw down the groundwater levels. The bore & jack work cannot be completed until the groundwater level has been drawn down below the proposed water main.

Upcoming Work: KUTTSHILL DRIVE WILL CLOSE TO THRU TRAFFIC ON MONDAY, 4/15

Next week, Dykema will begin installing water main along Kuttshill Drive. It is anticipated that the water main will take two weeks to complete. Kuttshill will remain close to thru traffic until the westbound lane can be rebuilt.

Marksman Contracting will bore & jack a steel casing across M-44 which will allow for the water main to be installed inside the casing without having to close M-44 to traffic.