The focus this week was Merrill Street east of Sanford with replacement of the sanitary sewer. Work continued on services as well.  Next week will be a busier week with work focusing on the west side of Merrill.

 

Work Completed This Week:

  • Sanitary Sewer mainline was installed on Merrill Ave. east of Sanford St.
  • Water on connecting homes to the sanitary sewer continued.
  • Water service replacements continued north of Strong Avenue.

 

Anticipated Work Next Week:

  • Placing sanitary sewer mainline on Merrill Ave. west of Sanford St.
  • Begin placing of storm sewer on Sanford Street north of Strong Avenue.
  • Continuation of connecting homes to the new sanitary mainline.
  • Continuation of connecting new water services.