  • Tree clearing continued along Pine Island Drive.
  • Montgomery continued water main construction along Pine Island Court.
  • Montgomery completed the bore & jack (trenchless construction method) under Pine Island Drive by installing a steel casing under the road at the south end of Pine Island Court.
  • Montgomery set up for the second bore & jack under Pine Island Drive at the north end of Pine Island Court and due to equipment malfunctions had to pause the steel casing installation.
  • Montgomery began roadside restoration at 9 Mile Road.

 

Next Week:

  • Pending equipment repairs, Montgomery will complete the bore & jack the north end of Pine Island Court.
  • Montgomery will complete water main construction on Pine Island Court.
  • Montgomery will install 8-inch water main in the steel casing at the south end of Pine Island Court.
  • Montgomery will continue to install 16-inch water main along Pine Island Drive where they left off and connect to the 8-inch water main in the steel casing at the south end of Pine Island Court.

 

Please contact any project representative below if you have questions or concerns.

 

What to Expect

  • April: Water main construction on Pine Island Drive.
  • Long Term: Water main construction is anticipated to be completed in July 2023.