This Week:
- Tree clearing was completed on Oakwoods Trail and Clearwater Court.
- CL Trucking completed water main construction on Clearwater Court.
- CL Trucking continued water main construction on Oakwoods Trail.
- The new water mains on Winding Ridge Trail and Garden Gate Drive and Court were pressure tested and disinfected.
Next Week:
- Tree clearing on Hidden Timbers Drive and Point High Drive will be completed.
- Water main construction completion on Oakwoods Trail.
- Water main construction on Hidden Timbers Trail.
- The new water main on Oakwoods Trail and Clearwater Court will be pressure tested to confirm there are no leaks and disinfected in preparation for water service installation. This will involve hydrant flushing – if you see water coming out of a hydrant and no one is around there is no need to be alarmed as this is part of the process.
If you would like to attempt to coordinate additional paving work on your driveway you may contact Rieth-Riley (CL Trucking’s paving subcontractor) to coordinate any extra work outside of the project scope that your expense.
Please contact any project representative below if you have questions or concerns.