Current Status/Progress Report

Water main construction started up again this week at the south end of Packer Woods Drive – see status map above for progress through this week. Dean’s Excavating plans to continue to construct water main out to Packer Drive next week and should be close to finishing water main construction on Packer Woods Drive by the end of next week. We appreciate your patience as access is limited throughout the workday for the houses that are south of the active construction area.

You should have received a letter from Plainfield Township with the Prequalified Contractor List enclosed. You may start to contact the contractor of your choice to start the process of getting your water service connected to your house when it becomes available in the next few months. If you have any questions about this process, please reach out to Jeremy Kamp (jkamp@preinnewhof.com).

Please contact any project representative to the left if you have questions or concerns.

 

What to Expect

Next Week

  • Water main construction to continue along Packer Woods Drive.