Progress Report

Dykema tested and disinfected the water main on Windstone Drive, water service installation will follow in the last week of April.

Information regarding how to connect your house to your new water service when it becomes available will be distributed to residents in early May.

Water main construction continued on Wolven Avenue moving from south to north. Water main construction began on Bent Tree Ridge and will be about halfway finished by the end of this week. See progress map above for locations where water main has already been installed.

Next week, water main construction will continue on Bent Tree Ridge and Wolven Avenue.

Please contact a project representative if you have questions or concerns.

 

What to Expect

Late April

  • Water main construction on Wolven Avenue and Bent Tree Ridge.

Long Term

  • As soon as the water main in one area is complete, tested, and ready for water service connections, Plainfield Township will communicate with you to start the process of installing water services on private property.
  • Dykema’s overall project schedule anticipates the total project, including road paving and lawn restoration, being complete in late August 2021.

There will be times that the area in front of your homes is torn up and you will have limited access to your home. Please let us know if you have any special access needs and we will do our best to make arrangements with you.

The contractor will be contacting you to make arrangements for mail delivery and garbage collection. Please let us know if you have any problems with this.

 

Projected Timeline

  • April – mid-May
    • Windstone Drive
  • April – mid-June
    • Wolven Avenue; 10 Mile Road to 43 North entrance
  • mid-April – mid-June 
    • Bent Tree Ridge Drive
  • May – June
    • Stoneridge Drive
  • May – July
    • 43 North
  • mid-June – July 
    • 11 Mile Road
  • July – August
    • Elstner Drive

Please share this information with your neighbors who may not have email or access to the internet.

Thank you for your patience and we look forward to a successful project in your neighborhood!