Construction staking is in process to show the location of the right-of-way and the location of the new water main. The new water main will be installed on the west or north side of the roads.

Dykema has marked and will continue to be marking which trees need to be cut down to allow for installation of the water main. Tree removal is scheduled to begin Monday, April 20.

Message boards will indicate that Chandler and Herrington will both be closed to through traffic; however, the roads will be open to local residents. Your driveways should always be accessible except for the short time it takes for the construction crew to install the water main across your driveway.

Please contact one of the project representatives (see contact information to the left) if you have questions or concerns.

 

What to Expect Next Week (April 20 – 24)

 