Progress Report:

  • Jackson-Merkey removed portions of the road and excavated their bore pits on either side of the railroad.
  • The 16-inch steel casing was installed underneath the railroad.
  • HDPE pipe fusing began.

Upcoming Work:

  • Jackson-Merkey will install the force main through the casing and west toward Temple Street.
  • After the force main is installed, the casing will be filled with grout and the pipe will be backfilled.