Progress Report:

  • N Court St – Water main tie-in at south end was completed. The tie-in at the north end is scheduled for Saturday 4/19. Installed the two water services on the west side of the road.
  • S Court St – Installed the storm sewer at the S Court/Lake intersection.
  • Walnut St – Installed the sanitary manhole and short run of 8-inch sanitary sewer.
  • WWTP – Installed the concrete thrust block, completed gravel drive repairs, and seeded the berm repair area.

Upcoming Work:

  • N Court St – Start grading the road and prepare the intersections for concrete crews to pour the concrete curb and gutter, and sidewalk ramps. Concrete work potentially the week of April 28th.
  • S Court St – Complete the water main tie-ins at the south end (Lake) and the north end (Walnut), install the water services.
  • Walnut St – Directional drill the 1.5” force main (Tuesday).
  • Vine St – Start installing water main at Vine/Walnut (potentially Wednesday).