Progress Report: The Contractor continued restoration efforts on the Grant Avenue intersection. The Contractor also started to set up traffic control and detour for the closure of Ferry Street between Taylor Ave and Grant Ave starting next week. The dewatering system was installed and the west lane of Ferry Street was removed from Grant Avenue to Taylor Avenue to prepare for water main installation to the south.

Upcoming Work: The Contractor will remove curb and gutter and driveways on the west side of Ferry Street next week starting from Grant Avenue and working south to Taylor Avenue. Starting early next week the Contractor will continue progress with water main construction to the south. Asphalt crews will be on site early to mid next week to install asphalt on the Grant Avenue intersection.

Extra Notes: Residents and motorists are reminded to stay clear of construction equipment and excavations on the project site. As water main construction continues south, access to each property will be affected and will change with the progress of construction.