After three weeks of work on the parking lot, here is where we stand on this Good Friday.

The contractor has accomplished the following work:

  • Continuing removals of the old storm system
  • Rerouting some storm sewer based on existing buried infrastructure
  • Nearly completed the new storm water collection system
  • Removing some sections of the sidewalk for installation of the new lighting bases.
  • Removing nearly all of the old lighting and electrical for the parking lot
 

Plans for next week, April 5:

  • Complete the storm sewer system
  • Clean up the work site, including the removal of poor material
  • Begin rough grading for aggregate
  • Layout and potentially install conduit for irrigation and electrical
  • Install new bases for new lighting
  • Install new gas service for the fire pit
 

Reminder

Please do not try to move barricades over the weekend or try to park in the parking lot. The parking lot is closed. All work planned is weather dependent, but the Contractor is still on schedule to be complete in late June 2021.