Work completed/in progress from the past two weeks:

  • 36″ transmission main construction progressed to Silver Ridge.
  • Water service verification and replacement, as necessary.
  • Continued staging pipe materials.
  • Directional Drill equipment for the Pine Creek crossing arrived on-site and was set up.
  • Large culvert east of Harderwyk Ministries was removed and replaced.
  • Road building began behind the pipe installation.

Anticipated activities for next week include the following:

  • Continue transmission main construction, water service verification and replacement, and road building.
  • Begin pilot hole drilling for HDD.
  • Close west entrance to Waukazoo. All school traffic will be directed to the east parking lot.