Progress Report

Dykema and Lees Trenching installed water services on Windstone Drive this week.

Information regarding how to connect your house to your new water service will be distributed to residents in early May.

Water main construction continued on Wolven Avenue moving from south to north. Dykema will be up to the 43 North development with water main construction along Wolven Avenue by the end of next week. Water main construction continued on Bent Tree Ridge and will be completed early next week. See progress map above for locations where water main has already been installed.

Next week, water main construction will continue on Wolven Avenue up to 43 North and will also start on Stoneridge Drive.

Please contact a project representative if you have questions or concerns.

 

What to Expect

Late April

  • Water main construction on Wolven Avenue and Stoneridge Drive.

Long Term

  • As soon as the water main in one area is complete, tested, and ready for water service connections, Plainfield Township will communicate with you to start the process of installing water services on private property.

Dykema’s overall project schedule anticipates the total project, including road paving and lawn restoration, being complete in late August 2021.

 

There will be times that the area in front of your homes is torn up and you will have limited access to your home. Please let us know if you have any special access needs and we will do our best to make arrangements with you.

The contractor will be contacting you to make arrangements for mail delivery and garbage collection. Please let us know if you have any problems with this.

Please share this information with your neighbors who may not have email or access to the internet. Thank you for your patience and we look forward to a successful project in your neighborhood!