Work Completed This Week

Prime Contractor – Kamminga & Roodvoets, Inc.

  • Placed 190 feet of Sanitary Sewer Main to Southern Ave.
  • Placed 12 Sanitary sewer laterals.
  • Placed 1,550 feet of watermain beginning at Merrill Avenue working south.
  • Pressure tested watermain from North end project limits to Strong Ave.

Anticipated Work Next Week

  • Continue to place and connect sanitary sewer laterals.
  • Complete placing main line sanitary sewer to phase 1 limits.
  • Continue placing watermain mainline.
  • Bacteria test watermain from North end project limits to Strong Ave to protect public health.

 

Contractor is not working Saturday 4/24/21.