Construction work resumed on Monday, April 20.As this issue is very dynamic and could change at any time, please check back frequently for project updates.

Work completed this past week:

  • The Union Pier intersection was closed and traffic detour around the work area was installed.
  • Pavement was removed in the Townline Road and Union Pier intersection.
  • Temporary water services were installed for local businesses near the Union Pier intersection served by New Buffalo Township water.

What to expect next week (April 27 – May 2):

  • Temporary road closure of Red Arrow Highway at Community Hall Road for water main installation. Anticipated closure date is April 27 or April 28.
  • De-watering equipment (large pumps, wells, etc.) will be installed in Townline Road and Union Pier intersection.
  • Sanitary sewer materials will start arriving.
  • Begin excavation for sanitary sewer installation.