Work completed this week:
- N Court St – Road building crews started grading the road and prepared for concrete crews to pour the curb and gutter.
- S Court St – Completed the water main tie-ins at the south end (Lake) and the north end (Walnut), installed the 2 water services. Road building crew started grading road.
- Walnut St – Directional drilled the 1.5” force main.
- Vine St – Started installing water main at Vine/Walnut moving northward.
Work anticipated next week:
- N Court St – Concrete crews will potentially be on site to pour curb and gutter at the intersections.
- S Court St – Road building crews will prepare the road cross section in anticipation for concrete crews.
- Vine St – Continue installing water main, testing and chlorinating once water main is installed, complete tie-ins of water main, and install water services.