This Week: The majority of the week was spent replacing concrete sidewalk and driveways on Daylor and Northgate. Montgomery continued to clean up the project site and began preparing for road and lawn restoration .
Next Week: Montgomery will continue lawn restoration work next week. Some of the existing concrete driveways were under the edge of the existing road. This will require that Montgomery patches the asphalt road at the end of these driveways. Montgomery will begin preparing these driveways for paving middle of next week.© 2025 Prein&Newhof, All Rights Reserved