Progress Report:

  • All 600 feet of HDPE force main and the force main discharge manhole have been installed in Sherman Boulevard. Jackson-Merkey is working on backfilling the force main today.
  • The bypass connection for the future lift station has been installed.

Upcoming Work:

  • The casing under the railroad will be filled with flowable concrete.
  • Concrete restraint collars will be poured on each end of the force main.
  • The force main will be pressure tested and backfill will continue.