Progress Report:
- All 600 feet of HDPE force main and the force main discharge manhole have been installed in Sherman Boulevard. Jackson-Merkey is working on backfilling the force main today.
- The bypass connection for the future lift station has been installed.
Upcoming Work:
- The casing under the railroad will be filled with flowable concrete.
- Concrete restraint collars will be poured on each end of the force main.
- The force main will be pressure tested and backfill will continue.