Work Completed This Week:

Gabe’s Construction completed site cleanup and demobilization. All equipment and materials are loaded for transport and stored at their temporary yard outside of the project limits.
They also completed connection of the crossing pipe to the Beechtree Street forcemain.
West Michigan Dirt Works completed concrete work and paving of Beechtree Street at Fulton Street. Top Course of the pavement is scheduled for this afternoon.

They also installed force main on Division Street and began removals of Exchange Street. Exchange Street is now closed from Division Street to Cutler Street.
Anticipated Work Next Week

West Michigan Dirtworks will stripe Beechtree Street and begin restoring the parking lot at City Autobody.
They will also continue installation of the force main on Exchange Street.
Comments

West Michigan Dirtworks remains on schedule for the milestone completion date to have Beechtree/Fulton intersection open along with the RV Park entrance drive open by May 1, 2019.