Upcoming Schedule:

  • Underground pipe installation between Eagle Lake and Crooked Lake will be completed today.
  • Balkema beginning restoration next week.
  • Work on the filter building and both pump stations will continue.
  • West Crooked Lake Drive is scheduled to be paved on May 6, 2024.