Construction crews have been very busy in Downtown Whitehall making improvements. Here is an update of the work performed this past week:
Pocket Park between Catchmark and Bell’s Furniture:
- Water Service was installed for new bathroom
- Excavated for footings for new seatwalls
Goodrich Park Parking Lot:
- 3 Trees Removed – Some were found to be hollow and diseased
- Silt fence installed, pavement removed for parking lot addition
- Topsoil stripped and stockpiled
Goodrich Park Fishing Pier:
- Boom installed at old fishing deck
- Old fishing deck removed
- Old sidewalk removed
Work expected the week of April 29, 2024:
- Electrical installation for lights at Goodrich Park Parking Lot
- Grading at Goodrich Park Parking lot, including addition of fill material and gravel
- Pouring concrete seat walls in Pocket Park
- Installation of new pilings for Fishing Pier
Work expected the week of May 6, 2024:
- Pour remaining concrete in Pocket Park
- Continue Grading and leveling at Goodrich Park Parking Lot
- Pour Concrete curb and Sidewalk repairs at Goodrich Park Parking Lot
- Begin Installation of new deck at Fishing Pier in Goodrich Park