Underground work continues with the installation of sanitary sewer main and laterals on Dryden from Johnson to Jefferson. Sanitary sewer installation will continue on Jefferson Street from State to Dryden and water services on Jefferson.

Work Completed This Week

  • Installation of sanitary sewer on Dryden street, Johnson to Jefferson.
  • Installation of sanitary laterals on Dryden.
  • Road reconstruction continues on Hart Street.
  • Storm sewer on Jefferson.

Anticipated Work Next Week

  • Installation of sanitary sewer on Jefferson, State to Dryden.
  • Sidewalks and curb on Hart Street.
  • Water services on Jefferson Street.

Please note:  Dave’s Party Store is accessible from Griswold Street and Wood Street, as well as State Street and Wood Street.