- Watermain has been placed along Burger between Goodwood and Tuscany.
- The main has passed all testing and has been tied into service.
- Crew have begun stubbing water services out to the right of way line.
- Watermain has been placed along Tripoli between Goodwood and Tuscany and on Tripoli Court.
- The watermain has been pressure tested and is in the process of being chlorinated.
- Watermain has been placed along Cimarron between Goodwood and Tuscany.
- The water main is being pressure tested.
- Watermain installation through the bayou on Burger between Tuscany and Tanglewood began and is nearing completion.
Work Upcoming
- The Contractor and the City of Grand Rapids will continue the pressure testing and chlorination of the watermain placed on Tripoli and Cimarron and begin the process of testing and chlorinating the main through the bayou.
- The contractor will continue stubbing water services on Burger and begin on Tripoli and Cimarron.
- The Contractor anticipates that a second crew will replace storm sewer on Burger between Tanglewood and Tuscany.
- Watermain installation on Tuscany is also slated to begin.
- Crews will begin restorative efforts in completed areas.