Work Anticipated Week of May 1, 2023
- Lowering of Manhole Covers and Water Valve Boxes
- Milling and removal of asphalt pavement
- Material and equipment deliveries to the job site
- Removal of concrete curb and gutter
Work Anticipated Week of May 8, 2023
- Removal of concrete driveway approaches between the sidewalk and curb
- Begin placement of new water main pipe