Current Status/Progress Report

Kamminga & Roodvoets (K&R) is scheduled to be on site in two weeks. The week of May 16 will include removal of trees in the road right-of-way which are necessary to install the water main, as well as removal of the existing asphalt which is necessary for the storm and sanitary sewer installation. K&R will be relocating mailboxes to a central location and setting up to start construction in the utility easement near Lakehurst.

Expect to see construction stakes and colored flags showing up in your yards in the next two weeks. Do not remove any of the flags or stakes, as they are marking existing underground utilities and providing information on where the new utilities are to be installed.

Please contact any project representative below if you have questions or concerns.

 

What to Expect

Middle of May

Long Term

 

Date: May 16Event: Begin tree removal on site
Date: May 16Event: Set up traffic control, pulverize existing roads, and begin sanitary sewer construction within the easement area east of Lakehurst
Date: May – Mid JulyEvent: Water main, sanitary sewer, storm sewer, and road reconstruction of Northville between Lakehurst and Leelanau
Date: July – AugustEvent: Water main, sanitary sewer, storm sewer, and road reconstruction of Leelanau between Northville and Manitou
Date: August – OctoberEvent: Water main, sanitary sewer, storm sewer, and road reconstruction of Northville between Leelanau and 5 Mile Road