This Week

Dean’s completed water main installation on Packer Woods Drive and Rogue Hill Court and began testing the new sections of water main. Trees were removed along Rogue Hollow Court in preparation for water main construction.

 

Next Week

Dean’s will complete water main construction on Rogue Hollow Court. Dean’s will also install water services to each individual house on Packer Woods Drive pending passing test results. Once all the water services have been installed, Dean’s will start to rebuild the road.