Contract 1 Work Completed in March:
  • Headworks startup and operation with live raw water
  • Grand Haven forcemain and local flows tied into new headworks
  • Completed decommissioning of old headworks
  • SE Primary Clarifier equipment installed
  • Painting in Activated Sludge Building (ASB)
  • East primary sludge pump startup
  • Finalized underground odor control piping for new headworks

 

Anticipated Work in April:

  • SE Primary Clarifier startup
  • West primary sludge pump startup
  • Finish pipe painting and labeling throughout the site
  • Site stormwater and underdrain piping
  • Various site restorations
  • Preparation and grading for sidewalk, site concrete, and paving