Work Completed This Week

  • The Young Avenue lift station plumbing is nearly complete.
  • The HMA pavement, curb and gutter, and driveway approaches on Crowley Street have been removed between Young Avenue and Laketon Avenue.
  • DVT Electric has installed the electrical panel and conduit for the lift station.
  • Force main has been installed on Crowley Street between Windsor Avenue and Laketon Avenue.
 
 

Anticipated Work Next Week

  • The general contractor, Kamminga & Roodvoets, has elected to take a two week break from the Beidler project due to concerns related to the risk of Covid–19 exposure. They are scheduled to temporarily shut down operations until April 20, 2020.
  • Miscellaneous subcontractor work may continue at the lift station in order to keep the project moving forward.
  • Kamminga & Roodvoets will be cleaning up the work site today so travel/access (for garbage pickup, mail deliver, and emergency vehicles) will not be impacted for local residences during the work stoppage.
  • We appreciate everyone’s flexibility during this crisis. We will continue to keep everyone updated on the status of the construction during this fluid situation.