Underground utility work will be starting next week Monday April 7th. The contractor is planning to start installing water main starting at N Court Street. The contractor is responsible for maintaining access to driveways throughout the installation, so if yours needs some attention, find a representative on-site and they will help you.
After N Court Street, the contractor will then shift to installing water main on Vine Street and S Court Street. Those would likely be starting mid to late April.