This Week:

  • Montgomery completed testing on Northgate (south of Eldon). Disinfection test results will be in on Saturday.
  • Montgomery installed water services on Daylor and Northgate (north of Eldon).
Next Week:
  • Montgomery will finish installing water services on Northgate (north of Eldon).
  • Montgomery will install water services on Northgate (south of Eldon) pending passing disinfection test results.
  • Sidewalks on Daylor and Northgate (north of Eldon) will be staked, and Montgomery will start grading in preparation for concrete crews to arrive on site within the next week.