Work on Mill Pond Trail continues to progress this week. Water service installation on Silver Creek continues.
Work Completed this week
- Approximately 1,200-FT of water main was installed on Mill Pond Trail progressing east from Silver Creek Road. The crews have completed two-thirds of the water main along Mill Pond Trail.
- Water service installations continue on Silver Creek Road with 4 new houses stubbed to the property line awaiting final connection.
Anticipated Work for the Coming Week
- Water main installation along Mill Pond Trail will continue.
- Water service installation will continue along Silver Creek next week Thursday. This work will be scheduled with each property owner.
Please be aware of the construction work, do not assume that equipment operators can see you. Do not approach heavy equipment.