This Week:
- Tree clearing continued along Pine Island Drive.
- Montgomery began water main construction along Pine Island Drive.
Next Week:
- Montgomery will pause water main construction along Pine Island Drive in order to install a steel casing under Pine Island Drive at Pine Island Court.
- Montgomery will begin bore & jack construction at the south end of Pine Island Court and install an 18-inch steel casing under Pine Island Drive which will have an 8-inch water main installed in it for Pine Island Court.
- Montgomery will begin water main construction at the south end of Pine Island Court and work north.
- Pine Island Drive is under a traffic shift between 10 Mile Road and 9 Mile Road for water main construction along Pine Island Drive.
- 10 Mile Road will close Monday, April 3, between Pine Island Drive and Algoma Avenue. Posted detour route is Pine Island Drive to Post Drive to US-131.
Please contact any project representative below if you have questions or concerns.