This Week:
- CL Trucking completed water main construction on Garden Gate Drive and Garden Gate Court.
- CL Trucking began water main construction on Oakwoods Trail.
- The new water mains on Winding Ridge Trail and Garden Gate Drive and Court were filled with water in preparation for testing next week.
Next Week:
- Tree clearing on Oakwoods Trail, Clearwater Court, Hidden Timbers Drive, and Point High Drive will be completed.
- Water main construction is anticipated be completed on Oakwoods Trail.
- Water main construction is anticipated to begin on Clearwater Court.
- The new water main on Winding Ridge Trail and Garden Gate Drive and Court will be pressure tested to confirm there are no leaks and disinfected in preparation for water service installation.