Work Completed This Week

  • Completed placing sanitary sewer main on Peck St. from Strong Ave. to North end of project limits
  • Began placing sanitary sewer main from Strong Ave. towards the South.
  • Placed 7 sanitary sewer manholes and 6 sanitary sewer laterals
  • Continued removing concrete pavement on Peck St.

 

Anticipated Work Next Week

The primary Contractor anticipates:

  • Continue removing concrete pavement and curb & gutter.
  • Continue placing main line sanitary sewer, and laterals.

 

No work is scheduled for Saturday, April 10.