Water main construction was completed in Windstone Drive this week. Next week the water main will be tested and disinfected before water services can be installed.

Water main construction began on Wolven Avenue at 10 Mile Road and will continue to move from south to north next week. See progress map above for locations where water main has already been installed.

Tree clearing continued this week and will be finishing up next week.

Please contact a project representative if you have questions or concerns.

 

What to Expect

Early April

  • Water main construction on Wolven Avenue.

Long Term

  • As soon as the water main in one area is complete, tested, and ready for water service connections, Plainfield Township will communicate with you to start the process of installing water services on private property.
  • Dykema’s overall project schedule anticipates the total project, including road paving and lawn restoration, being complete in late August 2021.

There will be times that the area in front of your homes is torn up and you will have limited access to your home. Please let us know if you have any special access needs and we will do our best to make arrangements with you.

The contractor will be contacting you to make arrangements for mail delivery and garbage collection. Please let us know if you have any problems with this.

 

Projected Timeline

  • April – mid-May
    • Windstone Drive
  • April – mid-June
    • Wolven Avenue; 10 Mile Road to 43 North entrance
  • mid-April – mid-June 
    • Stoneridge Drive
  • May – June
    • Bent Tree Ridge Drive
  • May – July
    • 43 North
  • mid-June – July 
    • 11 Mile Road
  • July – August
    • Elstner Drive

 

Please share this information with your neighbors who may not have email or access to the internet.

Thank you for your patience and we look forward to a successful project in your neighborhood!