Work Completed this Past Week:
- The Railroad replaced the tracks across Glenside in a nice coordinated effort with the City’s project
- Storm drainage pipes were installed and connected on the north side of the railroad
- Additional pavement, curb and driveway removals took place at the north end of the project near Wesco
- Water main work crossing Glenside for additional fire hydrant
Work Anticipated Week of August 14, 2023
- Completion of the storm drainage pipe and structures and connection to the existing system south of the railroad
- Completion of the new rail crossing
- Preparations for new road base gravel material to be installed
Work Anticipated Week of August 21, 2023
- Grading of the roadway base gravel material
- Preparation for new concrete curb and gutter
Construction will still remain on schedule for being completed in September 2023.