Work Completed this Past Week:

  • The Railroad replaced the tracks across Glenside in a nice coordinated effort with the City’s project
  • Storm drainage pipes were installed and connected on the north side of the railroad
  • Additional pavement, curb and driveway removals took place at the north end of the project near Wesco
  • Water main work crossing Glenside for additional fire hydrant

 

Work Anticipated Week of August 14, 2023

  • Completion of the storm drainage pipe and structures and connection to the existing system south of the railroad
  • Completion of the new rail crossing
  • Preparations for new road base gravel material to be installed

 

Work Anticipated Week of August 21, 2023

  • Grading of the roadway base gravel material
  • Preparation for new concrete curb and gutter

 

Construction will still remain on schedule for being completed in September 2023.