Maple Street: Concrete curb, ADA ramp and driveway work is underway and is planned to be complete by the end of the week. Maple Street base paving is planned for next week.

Lincoln Street: The water main to the South of Maple Street has passed disinfection testing. This week, connection of water services is underway and is planned to be completed by the end of the week. Sanitary lateral construction is planned to be complete by the end of the week. After sanitary lateral construction has been completed, storm sewer construction is planned to begin and will continue next week.