This Week:
- B&L Excavation continued water main construction on Freska Pines.
- Private water service work continued.
Next Week:
- B&L Excavation will complete water main construction on Freska Pines.
- The new water main in Freska Pines will be pressure tested to ensure there are no leaks and disinfection testing will take place after a passing pressure test.
- Utility companies will be on Wateredge Drive to flag existing utilities in preparation for water main construction to begin.
- B&L Excavation will begin water main construction on Wateredge Drive after the existing utilities have been flagged. It is anticipated that this will take place next week while the water main on Freska Pines is being tested.
Please contact any project representative if you have questions or concerns.