Work Completed This Past Week
- Final grading of road base gravel
- Placement of the first course of asphalt
- Raising manhole castings and valve covers to the final pavement level
- Topsoil and restoration has begun
Work Anticipated Week of August 14, 2023
- Completion of the raising of all manhole covers
- Topsoil, seeding and restoration will be completed
- Punchlist items will be generated and worked on
- Cleanup and removal of equipment, excess materials
- Final course of asphalt will be placed by the end of the week
- Additional cleanup and removal of traffic control barricades and signage
PROJECT WILL BE COMPLETED ON SCHEDULE!!!