Work completed/in progress from the last update:

  • Transmission main installed up to Wendy’s at River/Lakewood intersection.
  • Transmission main pressure test between east HDD pit to Holland Charter Township maintenance building complete.
  • Easement storm sewer for road reconstruct project completed.
  • Shoulder and topsoil restoration between 152nd and 144th.
  • Mobilized mobile groundwater treatment system.
  • Continued with Holland Township 16″ water main installation.
  • Road resurfacing project milled between Lakeshore and 144th. Leveling complete from Lakeshore to 152nd. Top course placement in progress between Lakeshore and 160th.

 

Anticipated activities for the upcoming week include:

  • Continue transmission main installation up to River intersection.
  • **Close River intersection on August 20.**
  • Continue Holland Township 16″ water main installation.
  • Install storm sewer between Aniline and Division for road reconstruct project.
  • Mill, level, and top remainder of road resurfacing project
  • Chlorinate transmission main from east HDD pit to Holland Charter Township maintenance building.
  • Connect HDPE drill pipe to 36″ transmission main at east HDD pit
  • Retore west HDD pit.