Progress Report

Belmont Avenue will be open to thru traffic by the end of the day Friday, August 13.

This week:
  • Dean’s completed 12-inch water main installation up to around Rogue Hill Court.
  • Dean’s completed the tie-in to the existing water main at Las Vegas Drive.
  • Dean’s pressure tested the first section of water main north of the Rogue River.
Next week:
  • Dean’s will disinfect the first section of water main north of the Rogue River.
  • Dean’s will continue to head north along Packer Drive and install 12-inch water main.
  • Pending passing disinfection tests, Dean’s plans to install water services on the first section of water main north of the Rogue River the second half of next week.

 

Once the water service stub has been installed out to the public road right-of-way in front of your house, you will receive a letter from our staff on site informing you that your water service is ready for connection. You will have sixty (60) days from the date of the letter to connect to the municipal water system. If you have not already contacted a private water service contractor about installing your free water service, you should do so as soon as possible to ensure you can meet the sixty (60) day connection requirement.

 

What to Expect

August
  • Water main and water service construction on Packer Drive up to the White Pine Trail.
September
  • Rogue River crossing
  • White Pine Trail crossing
Long Term
  • Water main and water services along Packer Drive and Van Dam Drive will be installed in 2021. Water main and water services along northern side streets and private drives off of Packer Drive will be installed in the spring of 2022.

 

Project Timeline

  • August
    • Water main construction along Packer Drive up to White Pine Trail and southern most private drive easement.
  • Labor Day Week
    • Water main construction crossing the Rogue River
  • September
    • Water main construction crossing the White Pine Trail and water service installation along Packer Drive.
  • Late September – Mid-October
    • Water main construction and water service installation along Van Dam Drive.
  • October
    • Water main construction along private drive easement just south of Rogue Hill Court.
  • April 2022
    • Water main construction along Packer Woods Drive
  • May 2022
    • Water main construction along Rogue Hollow Drive and Rogue Hill Drive