Progress Report

This week:
  • Schippers completed the final water main tie-in at 5 Mile Road and Plainfield Avenue.
  • Schippers continued road work on Bonneville Drive, north of Brisam Street, and court streets.
  • Schippers removed existing concrete curb and gutter in preparation for the new curbs to be poured.
  • Schippers concrete subcontractor, M&S Construction, poured new concrete curb radii at intersections and in the cul-de-sacs.
Next week:
  • Schippers will continue to do road work and get the north half of Bonneville Drive and the court streets ready for asphalt to be placed.
  • Schippers concrete subcontractor, M&S Construction, will finish pouring new concrete curb radii at intersections.
  • Schippers will work on project clean up.

 

Schippers landscaping subcontractor, H&K Landscaping, will be on site over the course of the next few weeks to spray all the weeds in the topsoil with a weed killer. Once the weeds have had a few weeks to die off, they will be back to finish spreading topsoil and complete the final lawn restoration in the beginning of September.

 

What to Expect

August
  • Road reconstruction north of Brisam Street
  • Parking Lot restoration at 5 Mile Road and Plainfield Avenue
  • Water Service conversions along Plainfield Avenue
September
  • Final restoration and project clean up

 

Project Timeline

  • August
    • Road reconstruction
    • Plainfield Avenue water services
  • Late August
    • Final paving